Between 1998 and 2002 the U.S. experienced an unprecedented power plant construction boom that consisted mostly of gas-fired, combustion turbine – based power plants. This surge in power plant construction had several driving forces, including electric power deregulation, the emergence of non-utility power producers, a sustained period of plentiful and inexpensive natural gas, and the availability of efficient and cost-competitive combustion turbine technology.
However, the foundation of this construction boom crumbled quickly. Deregulation of the electric generation industry stalled with the California energy crisis. Non-utility power producers sold out or eventually went bankrupt. Finally, gas prices rose dramatically and today appear to have stabilized at two to three times their price in 2000.
One of the primary considerations in making a decision whether to develop a repowering or a new brownfield project is the life-cycle cost. The life-cycle cost of a new brownfield unit may be more favorable than that for repowering.
As the demand for electricity continues to grow, new base-load generation is needed. For a variety of reasons, coal-fired generation appears to be the most likely candidate for meeting this demand. The run-up in gas prices has been sustained for several years, sparking a strong interest in coal and other solid fuel – fired power plants.
In addition to an increase in greenfield plants, Stone & Webster Management Consultants Inc. (Stone & Webster Consultants) has seen increased interest in solid fuel repowering of existing oil- and gas-fired boilers. The primary reason for this interest is that repowering an existing gas- and/or oil-fired power plant with solid fuel boilers potentially has a lower capital cost and lower development risk than developing a new greenfield solid fuel – fired power plant.
Technology Selection Considerations
The issues that drive the technology selection decision for a solid fuel facility are:
- The fuel
- The desired unit size
- Solid waste disposal considerations
Pulverized coal (PC) technology is probably the economic choice for any plant that will burn coal — whether it’s bituminous, subbituminous, or lignite — as the primary fuel. Circulating fluidized-bed (CFB) technology will be the choice for petroleum coke or other “opportunity” fuels.
Based on the current state of CFB development, if the unit size is greater than 400 MW, the CFB plant will require two boilers, compared with a single boiler for a PC plant. The single-boiler PC plant would normally be more cost effective, unless the fuel selection favors CFB technology.
The cost of solid waste disposal can have a significant effect on a plant’s life-cycle costs. Units burning subbituminous coal can usually sell the flyash. In addition, there is potential for selling the gypsum produced by wet flue gas desulfurization (FGD) systems.
For PC units using dry FGD, separating flyash from the sulfur capture waste may make the ash more marketable. In contrast, flyash and sulfur capture wastes can not be separated with CFB technology. As a result, CFB solid wastes are not as marketable.
Repowering vs. New Brownfield Considerations
One of the primary considerations in making a decision whether to develop a repowering or a new brownfield project is the life-cycle cost. The life-cycle cost of a new brownfield unit may be more favorable than that for repowering, for the following reasons:
- A new brownfield unit eliminates the issue of unknown equipment condition and the risk of cost increases due to those unknowns.
- A new brownfield unit can be expected to have a lower heat rate, higher availability, higher capacity factor, and lower operation and maintenance (O&M) costs compared with a repowered unit.
- A single new brownfield unit can simplify the repowering of a site with multiple small units with different steam conditions.
Environmental Considerations
A number of environmental issues typically impact the design and economics of a repowering project. Many are specific to the project location and current operations of the generating units to be repowered. However, the air emissions control requirements for every repowering project have a major impact on space requirements, site layout, transportation requirements, solid waste disposal, and life-cycle costs.
“Netting out” of New Source Review requirements is unlikely for facilities with existing oil- or gas-fired units that are to be repowered with solid fuel boilers. This is due to low air emission rates and low historical capacity factors that are typical for oil- and gas-fired facilities. If the new boiler is located in an attainment area, as classified by the National Ambient Air Quality Standards, the new boiler will be required to install best available control technology (BACT) for each pollutant emitted in excess of its significance level.
If the repowering site is located in a nonattainment area, the air pollution control (APC) equipment for the nonattainment pollutant will need to meet the lowest achievable emission rates and obtain emission offsets. Sites that are located in a nonattainment area for any of the major pollutants are probably not a good choice for a solid fuel repowering project. Table 1 provides a summary of typical BACT selections for new solid fuel power projects.
Table 1. Typical BACT selections for solid fuel repowering options. Source: Stone & Webster
The final Clean Air Mercury Rule includes a cap-and-trade system for new and existing coal-fired generating units. This rule will apply to repowering and new brownfield projects. Based on the rank of coal used and the FGD system employed, both of the options would be subject to New Source Performance Standards for mercury. There have been a number of Powder River Basin (PRB) coal projects with dry FGD that have mercury emission limits requiring activated carbon injection systems.
The majority of recently permitted PC projects using eastern bituminous coals have not required additional mercury controls. These projects have relied on the “co-benefit” mercury reductions expected from the air pollution control system for SO2, NOX, and PM. Control of carbon monoxide (CO) and volatile organic compounds (VOC) emissions from PC and CFB boilers can be accomplished with good combustion practices.
Section 316(b) of the Clean Water Act requires the Environmental Protection Agency to ensure that the location, design, construction, and capacity of cooling water intake structures reflect the best technology available. This requirement is to protect aquatic organisms from being killed or injured by impingement or entrainment. The Section 316(b) rules require that all new generating facilities be cooled with cooling towers or use the equivalent cooling water of a wet cooling tower facility for the site. However, Phase II of this rulemaking for existing electric generating plants provides more flexibility for existing stations to retain their once-through cooling water usage.
The new rule allows a facility to repower or replace its existing steam turbine condenser and cooling water system with a new cooling system that uses up to 10% more once-through cooling water than the equipment it replaces. This allows older power plants to retain once-through cooling for repowering or for a new brownfield replacement unit. It should be understood that the cooling system must eventually meet new impingement and entrainment performance standards required by the Phase II rules. A submittal of a Comprehensive Demonstration Study is required no later than January 7, 2008.
A new solid fuel power plant will need to consider, in its design, the issues associated with:
- New sources of fugitive dust emissions associated with material-handling operations.
- Water requirements as influenced by the condenser cooling options.
- Limitations on the wastewater flows and chemical composition contained in the National Pollutant Discharge Elimination System permit.
- Additional space for on-site landfills for ash and FGD by-product disposal from the new or repowered PC or CFB boilers.
- The potential for increases in sound levels above background levels at sensitive receptors that may be specified in local sound ordinances.
- Potential site contamination, particularly at oil-fired facilities, that could have an impact on site preparation costs and the ultimate site plan.
- Local concerns with increased truck or rail traffic associated with delivering fuel and FGD reagents to the site. Removing ash and FGD by-product from the site should be assessed early in the project development.
- The location of on-site wetlands or critical habitats that could potentially affect the site layout and the ability to develop on-site landfills.
Site Arrangement and Space Allocation
When considering repowering or a new brownfield development at an existing oil- or gas-fired station, land availability is often the most critical issue. The space required for new solid fuel boilers, the associated pollution control equipment, and the stack will be greater than the space made available by removing old boilers and associated equipment.
A major reason for additional space is to accommodate fuel handling and storage, reagent handling and storage, solid waste storage and disposal, and a larger stack. Lack of space may eliminate the repowering option for some sites. The main purpose of performing a site layout as part of a repowering study is to determine if there is sufficient space for all the necessary equipment; it will also determine if there are any fatal flaws.
The “power block” is considered to be the boiler, turbine (brownfield development), air pollution control equipment, draft fans, and stack. This is assuming that the PC and CFB units will have APC equipment that meets BACT requirements. Table 2 shows the approximate area required for a 500-MW unit using a conventional arrangement with the APC equipment in series with the boiler.
Table 2. Power Block size nominal 500-MW unit. Source: Stone & Webster
The storage requirements for fuel and reagent are major issues at any site being considered for solid fuel repowering. Storage requirements are a function of the reliability of the transportation method and the length of the haul. Fuel and reagent storage requirements were calculated based on a conventional arrangement of open storage piles with a small active pile and a larger long-term pile. In addition, the capacity factor was assumed to be 100% for the 60-day period, and the long-term pile was assumed to be 50 feet high.
Figure 1 shows the land requirements for fuel and reagent storage; Figure 2 shows the total land needed for 500-MW PC and CFB plants burning petroleum coke, Pittsburg No 8, and PRB fuels.
1. Fuel and reagent land requirements. Source: Stone & Webster
2. Total land requirements. Source: Stone & Webster
As shown in Figure 2, the total land requirement, depending on the technology and fuel selections, for a 500-MW PC or CFB plant ranges between 11 and 15 acres. The land areas shown do not include the area necessary for a new turbine building, which would be required for a new brownfield project. However, a turbine building would only occupy approximately 1 acre. As a consequence, the acreage necessary for a new unit is not significantly different from that needed for the repowering option. In addition, the land area requirements shown do not include the 40 acres needed for a rail loop to accommodate full-unit trains.
Reuse of Existing Equipment and Systems
The primary attraction of repowering an existing unit, compared with placing a new brownfield unit at the same site, is the potential cost savings associated with the reuse of a large portion of the existing unit. On the surface, reuse of a large portion of the turbine and balance-of-plant systems may appear to be very cost effective. However, a review of the capital cost estimates for a variety of coal- and petroleum coke – fired repowering projects indicates that the costs to repower an existing unit can approach the cost of a new brownfield unit on the same site burning the same fuels.
The major equipment/systems that are usually considered for reuse in a repowering project include:
- Steam turbine and associated equipment
- Generator, exciter, and voltage regulator
- Condenser and circulating water system
- Closed cooling water system
- Condensate system
- Feedwater system
- Water and wastewater treatment systems
- Electrical systems
- Compressed air system.
Careful condition assessment reviews, including appropriate nondestructive examination tests, must be conducted on any equipment that is intended for reuse.
Repowering Evaluations
Stone & Webster Consultants has developed tools for rapidly performing initial repowering evaluations. The primary tool is an exclusive computer model composed of modules for various sizes and types of power plants. These modules include detailed capital cost breakdowns, typical project schedules, performance, availability, O&M costs, and environmental emissions data.
Additionally, the modules can be adjusted for different geographic locations and scaled to different plant capacities. They can also be altered for a repowering application where existing equipment is used as-is, upgraded, or expanded. Information from the cost and performance modules is used in an economic model for evaluating repowering and new brownfield projects.
Table 3 shows the economic model results comparing the repowering of two gas-fired 250-MW steam units using PRB coal-fired CFB boilers with a new brownfield unit using either a single 500-MW supercritical PC unit or a 500-MW CFB unit using two CFB boilers connected to a single subcritical steam turbine.
Table 3. Economic results: Repowering versus new brownfield unit. Source: Stone & Webster
The results show that, despite the $112 million savings in project capital investment for the CFB repowering project compared with a new PC unit, the new PC unit would result in a lower levelized cost of electricity. Although the CFB repowering project is $158 million less costly than a new brownfield CFB project, the resulting levelized cost of electricity is about the same.
On the other hand, if a supercritical cycle is selected for the new brownfield CFB project, it would be more economic than repowering. This evaluation shows that the lower capital cost of a repowering project can be easily overcome by the improved performance and lower O&M cost of a new brownfield project.
Table 4 presents another example of the model output for a comparison of repowering two gas-fired 350-MW steam units with petroleum coke – fired CFB boilers versus a new brownfield unit comprising two 350-MW CFB boilers and one steam turbine.
Table 4. Comparison of repowering versus new brownfield unit. Source: Stone & Webster
In this second example, the lower capital cost of the repowering option overcomes the improved performance of the new units, thus providing a lower levelized cost of electricity.
The two examples demonstrate how site-specific conditions, fuel selection, and technology selection can affect the final economic comparison. They also show how close the economic comparison can be between a repowering project and a new brownfield development at the same site. In order to evaluate the least-cost option based on site specific conditions, fuel requirements and technology selections, a feasibility study is essential.